Construction Update
We are excited to announce that the abatement phase of our project began mid-February and is scheduled to be completed by April, with demolition set for April & May. Our building site at 130 East Cordova which housed our shelters facilities and administration will be cleared by early June. The site will then be ready for the excavators and pouring of the foundation in June. This is an exciting milestone for our Nine Stories of Hope Campaign.